By Matthieu Caillaud · Founder, oceanographer
A well-scoped metocean study starts from the engineering decision — structural design, offshore campaign scheduling or cable-corridor screening — rather than a data catalogue. Choosing between ERA5 global reanalysis, regional wave hindcasts, tidal models and in-situ measurement campaigns directly governs extreme-value reliability, lead times (from 5 working days to several months) and project cost.
1. Which data source fits which project need?
Early in an offshore wind, port or submarine cable project, teams often fall into one of two traps: relying on a coarse global reanalysis too close to shore, or commissioning a heavy measurement campaign before the site is even locked. The table below compares the five main data sources used in practice.
| Source | Resolution & period | Strengths | Main limits | Recommended use |
|---|---|---|---|---|
| ERA5 (ECMWF) | ~31 km (waves ~0.36°), hourly, since 1940 | Global coverage, very long homogeneous record, immediately available | Under-resolves coastal gradients, shallow-water effects and local storm peaks | Feasibility, offshore wind/wave climatology, early operability, preliminary design |
| Regional wave hindcast (RESOURCECODE / WW3) | Unstructured coastal mesh down to ~200 m, 30 years (1993–2022) | Captures coastal wave transformation (refraction, bathymetry, breaking) | Bounded regional footprint (European Atlantic, Channel and North Sea for RESOURCECODE) | Nearshore offshore wind, submarine cables, port structures, seabed shear stress |
| Coastal currents (hourly CMEMS, FES2022, CROCO) | From a few km (CMEMS) down to tens of metres (CROCO) | Resolves tides, slack-water timing and coastline/bathymetry interaction | A dedicated 3D CROCO setup requires scoping, calibration and dedicated compute | Macro-tidal zones (Channel, Iroise, Bay of Seine), port approaches, seabed mobility |
| Offshore currents (GLORYS12) | 1/12° (~8 km), global Copernicus Marine reanalysis | Homogeneous multi-decade basin circulation in deeper water | Does not resolve coastal tidal currents or fine shelf dynamics | Deep-water sites, offshore corridors, open-boundary forcing for regional models |
| In-situ measurements (buoy, ADCP, tide gauge) | Pointwise, high frequency, 6 to 24 months | Local physical ground truth required for final certification | High cost, long deployment lead time, too short alone for 100-year extremes | Hindcast calibration and validation, detailed design and regulatory dossiers |
2. Matching study scope to project stage
Rather than buying a monolithic study at concept stage, aligning scope and modelling effort with the decision milestone keeps cost and schedule under control. Below are the four standard formats we deliver, with their methods and typical turnaround times.
| Scope | Typical use case | Key methods & data | Deliverables | Typical lead time |
|---|---|---|---|---|
| Fixed point | Mooring, landfall, single structure location | ERA5 (1993–2024 default), wind/wave roses, Hs/Tp scatter, GEV/Gumbel/POT-GPD extremes (1–100 yr), persistence; optional currents | PDF report, JSON data, PNG figures | 5 working days |
| Route profile | Maritime corridor, transit or export route | Multi-point analysis along the route, segment-by-segment exposure, governing leg identification, seasonal weather windows | PDF report, segment profile, JSON, PNG | 10 working days |
| Offshore wind / MRE site | Fixed or floating wind farm, substation, offshore structure | Design extremes up to 100-year return period, joint Hs/Tp distributions, IFORM environmental contours, wind-sea vs swell, DNV-ST-N001 windows | Extended PDF report, persistence tables, JSON, PNG | 15 to 20 working days |
| Cable corridor atlas | Pre-survey screening for power or telecom submarine cables | Combined wave-current bottom shear stress (Soulsby 1997), Shields threshold, 30-year POT-GPD extremes (500 m grid), A* optimal corridor, optional ADCP/core calibration | PDF report, GeoTIFF rasters, NetCDF, GeoJSON/KML corridor | 3 to 8 weeks |
For full deliverable details and options, see our Metocean study and Cable corridor atlas pages.
3. Extreme values and uncertainty: what to require
A 100-year return level (Hs or current speed) quoted as a bare single number without a confidence interval is not actionable for structural engineering. Three safeguards separate a rigorous metocean study from a raw statistical dump:
- Tail-appropriate extreme-value statistics: Peaks-Over-Threshold (POT-GPD) with threshold-stability checks, or annual maxima (GEV / Gumbel), paired with joint (Hs, Tp) environmental contours via IFORM when wave period drives structural response.
- Explicit confidence intervals: bootstrap 95 % confidence intervals reported alongside every return level to quantify sampling uncertainty, especially over 30-year hindcasts.
- Validation against public observations: whenever a wave buoy (e.g. CANDHIS), tide gauge (SHOM) or satellite altimetry track lies nearby, the study should quantify hindcast bias and RMSE on the zone (see our ERA5/MFWAM audit against altimetry and CANDHIS buoys).
4. Operability and DNV-ST-N001 weather windows
During installation (foundations, hook-up, cable burial) or O&M (CTV transfers), waiting-on-weather cost often outweighs uncertainty in 100-year extremes. The DNV-ST-N001 standard requires evaluating the reference duration TR = TPOP + TC (planned operation time plus contingency) and applying an alpha reduction factor to the operational limit OPLIM to account for forecast uncertainty beyond short lead times.
You can explore the continuous sensitivity to OPLIM and seasonality across 31 years of ERA5 in our interactive weather-window demo, or read our full analysis of DNV-ST-N001 cable-lay operability in the English Channel.
5. Limits stated clearly upfront
A study built on public reanalyses and hindcasts (ERA5, GLORYS12, RESOURCECODE) delivers a reproducible decision basis in days, but is not a substitute for a regulatory in-situ measurement campaign or a geophysical survey. In nearshore areas with steep bathymetric gradients or complex structures, uncertainty increases and calibration against local measurements (ADCP, wave buoy, cores) is recommended as soon as the project enters detailed design.
Preparing a tender or feasibility study? Share your coordinates and operational thresholds: we will scope the leanest data combination that fits your decision milestone.
Sources and references
The metrics, comparisons and maps specific to this article are OceanData Consulting results and calculations; the links below document the datasets, standards and publications used.
Facing a similar modeling or metocean data challenge?
From physical model calibration to operational AI post-processing, we help turn marine observations into validated, decision-ready forecasts.
Frequently asked questions
Is ERA5 sufficient for a nearshore metocean study?
ERA5 (~31 km, since 1940) works well for feasibility, offshore sites and early seasonality screening. In nearshore zones with steep bathymetry or strong tides, it should be complemented by a regional wave hindcast (RESOURCECODE / WW3), coastal currents (hourly CMEMS, FES2022 or CROCO) and, at detailed-design stage, calibration against in-situ measurements.
What are typical turnaround times for a metocean study?
Depending on scope: 5 working days for a fixed point, 10 working days for a route profile, 15 to 20 working days for a full offshore wind / MRE site (extremes up to 100-year return period, IFORM contours, DNV-ST-N001 persistence) and 3 to 8 weeks for a submarine cable corridor atlas with A* routing.
What is the difference between a metocean study and a cable corridor atlas?
A metocean study quantifies wind, waves, currents, extremes and weather windows at a point, route or site. A cable corridor atlas adds bottom boundary-layer physics (Soulsby 1997, Shields threshold), sediment mobility, extreme scour and A* least-cost corridor routing on a 500 m grid.
Does a hindcast study replace an in-situ measurement campaign?
No. It delivers a reproducible basis for feasibility, preliminary design or survey targeting in days, whereas a buoy or ADCP campaign takes 6 to 24 months. For final certification or detailed design in complex coastal areas, local measurement calibration remains necessary.